5 May 2026 · 17:00 PT · 30 minutes · 20 in the room
Agenda · five movements
01Nick opens with the room.
02MicroLink in five minutes: what we are, what's different, what's live.
03San José: the flagship deployment, in shape.
04Eight zones of collaboration, each with a named owner.
05What comes next: three asks, one closing thought.
Joining from NVIDIA
Jumbi Edulbehram, PhDVP Global BD, Public Sector · host
Andria ZouSr Director, Global AI DC Strategies
Jared CarlGlobal AI Data Center Lead
Karthik MandakolathurProduct Manager, Magnum IO
Elad BlattHead BD, Telco Networking
Ben GueretTechnical Program Manager
Danny ZaidifardBD, Strategic Partnerships
Alex PazosSr BD Mgr, Smart Spaces
Claudio FassiottiEMEA Smart Spaces, Sales
Wendy Zhu, PhDValidation, partner-adjacent
Chris ChoCloud and partner technical
Rodney ShetlerPre-sales and Solutions Eng.
David MessinaInception VC Alliance, adjacent
In the room · MicroLink Data Centers
Nick SearraCEO and Co-Founder
Sancha OlivierCEO, Design
Shane PatherChief Technology Officer
Andrew ThomasChief Commercial Officer
David HasslerHead of Sales
Jeff SvedahlCEO, MicroLink Edge
Deniz AkgulCapital & Investment Advisor
Sovereign AI is the production of intelligence using a country's own infrastructure, data, workforce, and business networks.
Jensen Huang · February 2024
We want to build the operational template, with you, here. Then take it everywhere.
01 · Thesis
Stacking MHP and compute waste heat at San José
A thermal-fit thesis for the ADFU upgrade and the Jacobs–MicroLink technology integration partnership.
Jacobs' Microbial Hydrolysis Process and MicroLink's compute waste heat are made for adjacent jobs at the San José–Santa Clara Regional Wastewater Facility. MHP is a post anaerobic digestion sidestream reactor at 75 °C that lifts biogas yield up to 36 percent at this site. MicroLink's 50 °C closed-loop waste heat sits at exactly the right tier for mesophilic digester heating and raw sludge preheat.
The thermal stack is additive: MicroLink takes the low-grade duty that today consumes recoverable cogen heat, freeing 8 to 12 megawatts of high-grade thermal capacity for the new MHP module and freeing the post-upgrade biogas surplus for monetisation through renewable natural gas injection at roughly $45 per MMBtu all-in.
IMAGE — HeroSan José RWF aerial, post-2022 cogen and dewatering builds, looking from north-west toward the bay.img-1-1
The core claim
The Jacobs cogeneration facility at San José rejects an estimated 8 to 12 megawatts of recoverable thermal energy to atmosphere today. The post-ADFU plant will produce 35,000 to 55,000 cubic metres per day of biogas surplus. MicroLink resolves both: a colocated heat sink that absorbs the rejected thermal energy and frees the biogas surplus for higher-value monetisation.
A 10 MW MicroLink deployment captures 8.5 MW thermal (85% of IT load), delivers ~6 MW to the digesters at 55–60 °C, and generates 2.3 MW of behind-the-meter electricity through an on-site molten carbonate fuel cell on freed biogas. Net grid draw drops 21%. CO₂ avoided: ~11,750 tCO₂e per year. We propose to anchor this as the first-of-kind reference deployment of a generalisable Jacobs–MicroLink integration system.
Three goals for the meeting
Goal 01
NCP onboarding track
A working session with Andria Zou's team on certification, NCX Infra Controller integration, and the ISV validation suite. We bring the live pod spec at 576 GPUs, three-loop thermal architecture, diesel-free 2N power. We'd like the onboarding playbook, with DGX-Ready Colocation as the realistic first-step framing.
Goal 02
DSX Max-P as a first-class mode
A roadmap commitment or co-development conversation with Karthik Mandakolathur on a thermal-output-maximising counterpart to Max-Q. Same API surface, opposite objective: maximise sustained heat delivery to the host process when the host demands heat. We have the field data to calibrate.
Goal 03
One named ISV introduction
A routing from Danny Zaidifard to the right NVIDIA-aligned partner for the Kubernetes and multi-tenant orchestration tier on the pod. Mirantis k0rdent is our hypothesis. We want NVIDIA's recommendation rather than picking blind.
San José–Santa Clara Regional Wastewater Facility at sunset · the flagship deployment site, 11 km from NVIDIA HQ.
02 · MicroLink
Build, own, operate. Industrial facilities.
01 Wastewater treatment
Server reject heat returns to anaerobic digesters at 35 to 38 °C. Biogas powers the load through molten carbonate fuel cells.
02 Breweries
Reject heat at 60 to 70 °C feeds wort heating and clean-in-place water as a baseload thermal source replacing steam.
03 Hotels and hospitality
Sub-MW edge pods deliver 60 °C water for laundry, kitchens, hot water, and pools. Gas displacement plus on-property compute.
04 Hospitals
Hospital-grade 24/7 baseload heat with the redundancy hospitals already have. Thermal resilience plus campus compute.
05 District heating
Direct feed of 65 °C water into a district network return loop. A year-round, weather-independent heat source.
06 Research campuses
University utility plants with district heating networks and on-site research compute demand. UW Seattle is canonical.
Service · 01
Sovereign AI for the public sector
Confidential Computing on Hopper and Blackwell. BlueField-3 multi-tenant isolation. Per-tenant clusters with sovereign weights and sovereign data, on city-owned land under municipal Joint Powers Authority.
Service · 02
Colocation and Neocloud
We secure each site through anchor-tenant colocation, then deploy MicroLink-owned compute on the remaining capacity as Neocloud.
80%Colo · anchor tenant
20%Neocloud · our servers
02.A · The portfolio · six projects, six host categories, one model
01 · Brewery
Anheuser-Busch · St Louis
The largest beer production site in North America. A pilot pod absorbing reject heat into wort and clean-in-place water systems. The first MicroLink deployment inside an AB InBev facility under the corporate technology partnership track.
Heat use60 to 70 °C reject heat to wort and CIP water, baseload steam displacement
Why thisBrewery as a host category proven at the largest US site. Gateway to the AB InBev portfolio.
Site qualifiedLOI signedDAConstructionOperating
Image · AB InBev St Louis
02 · Wastewater
MWRD Stickney · Chicago
The largest wastewater treatment plant in the world. 45 MW total committed capacity, phased. 5 MW first phase scaling to 10 MW second phase, with subsequent phases as the partnership matures.
Plant~2.4 billion litres per day [700 MGD]. 2.3 million residents, 124 communities.
Why thisScale. If we deploy 45 MW at Stickney, the precedent is set globally.
Site qualifiedLOI signedDAConstructionOperating
Image · Stickney WWTP aerial
03 · Wastewater · NVIDIA design partnership track
San José and Santa Clara RWF · California
5 MW first phase scaling to 15 MW total over two phases at the city-owned regional wastewater facility, 11 km [7 mi] from NVIDIA HQ. The flagship sovereign municipal AI cloud deployment.
Capacity15 MW over two phases: 5 MW Phase 1, 10 MW Phase 2
EngineeringJacobs Solutions, ADFU contract awarded January 2026
Why thisFirst US municipal sovereign AI cloud. Only WWTP-coupled NCP candidate in California.
Site qualifiedLOI signedDAConstructionOperating
Image · San José RWF aerial
04 · Wastewater
Newtown Creek WRRF · Brooklyn, NYC
10 MW deployment integrating with the eight egg-shaped digesters that have made the site one of NYC's most photographed civic infrastructure landmarks. The first East Coast sovereign municipal AI candidate.
Heat use35 to 38 °C return into mesophilic anaerobic digesters
Why thisEast Coast anchor. Civic visibility. NYC's tech and finance ecosystem in reach of one site.
Site qualifiedLOIDAConstructionOperating
Image · Newtown Creek digester eggs
05 · District heating
University of Washington · Seattle
A pod at the West Campus Utility Plant Annex (P-4), tied into UW's Energy Renewal Plan. Phase 1 at 1 to 2 MW IT load, Phase 2 scaling to 3 to 5 MW. Reject heat at 65 °C feeds the new Primary Heating Water loop directly.
Capacity1 to 2 MW Phase 1, 3 to 5 MW Phase 2 with WCUP Annex programme completion
Why this93% of UW campus emissions are gas combustion. Research compute repatriated to campus.
Site qualifiedLOIDAConstructionOperating
Image · UW WCUP Annex
06 · Hospitality
Choice Hotels · 25-site pilot
A 25-site initial deployment scaling to 200 properties under Phase 2, structured as the MicroLink Edge SPV. Sub-MW pods per property using NVIDIA Jetson Orin and IGX at the host edge, federated back to regional cores at MicroLink WWTP and brewery sites.
LeadJeff Svedahl, CEO MicroLink Edge SPV
ArchitectureJetson Orin / IGX at host edge, Spectrum-XGS site-to-site federation
Why thisFirst hospitality-anchored distributed compute network. Each hotel a regional inference point.
Site qualifiedLOI draftedDAConstructionOperating
Image · Choice Hotels pod
02 · MicroLink
Heat recovery infrastructure for data centres
2.1 — Who we are
MicroLink Data Centers builds heat recovery infrastructure for data centres. We design, build, and operate the thermal layer that turns compute waste heat from a problem into a resource. Our purpose-built systems — covered under provisional patent ML-IND-001 — sit at the boundary between AI compute and the host process loop, capturing 50 °C closed-loop heat from rack-level liquid cooling and delivering it into industrial, utility, and public-sector heat sinks where it does useful thermodynamic work.
The architecture is small-footprint, modular, and deployable inside the operating fence line of an existing public-sector or industrial site without requiring greenfield land development or new high-voltage transmission. Wastewater treatment plants are the first category. The thermal-fit logic extends to district heating networks, food processing facilities, and any industrial host with a low-grade thermal demand that compute waste heat can serve.
We are a public-sector AI infrastructure partner. We deploy on public-sector sites and we work with public-sector teams to stand up sovereign and municipal AI capability. NVIDIA is our primary go-to-market partner; we are in final stages of NVIDIA Cloud Partner programme approval, expected within two weeks, with two parallel partnership tracks: deployment partnership at this San José site, and global public-sector partnership covering shared infrastructure for sovereign and municipal AI compute.
IMAGE — MicroLink aerialSchematic aerial of a MicroLink integration. The compute facility (right) connects through a closed thermal loop to the host's process infrastructure (left). The architecture is sized for behind-the-fence deployment at industrial and utility sites. [render: what_is_microlink_aerial_png.png]img-2-1
IP positionML-IND-001 (prov.)
Heat captured85% of IT load
Energy reuse< 0.5 ERE
CO₂ avoided~1,175 tCO₂e per MW per year
Footprint150 m² per MW deployed
2.2 — The NVIDIA partnership
MicroLink is in active partnership discussions with NVIDIA on two parallel tracks: a deployment partnership covering this San José site, and a global public-sector partnership covering shared infrastructure for sovereign and municipal AI compute. Both tracks are pending NVIDIA Cloud Partner programme approval, expected within two weeks. We can speak to additional detail once approval is granted.
2.3 — Why we are at this table
The MicroLink technical thesis was first articulated by Jacobs itself. Debbie Seibold Egeland's 2023 Driving Sustainability in Data Centers white paper identified the colocation of compute infrastructure with wastewater treatment as a structural decarbonisation opportunity. The 2022 six-part Hydrogen from Wastewater series by Andrew McLeod and Stephen Horrax laid out five pathways from biogas to hydrogen, of which Pathway 5 — steam methane reformation of upgraded biomethane — is the most commercially relevant in the 2026 California market.
Jacobs published the thesis. We have built the technology that makes it deployable. The opportunity at San José is unique: the City has just contracted Jacobs to build the largest active MHP deployment in the United States. The site has approximately 750 acres (305 hectares) of freed industrial-zoned footprint inside the operating fence line. The cogeneration system rejects 8 to 12 megawatts of recoverable heat to atmosphere today.
IMAGE — Document coverEgeland 2023, "Driving Sustainability in Data Centers", Jacobs white paper.img-2-2
Source: Jacobs, Hydrogen from Wastewater (2022). Reproduced for technical context.
Site plan — RWF clarifier basins and treatment cells.
"Jacobs published the thesis. We have built the technology that makes it deployable."
Site context — RWF in its wider regional setting.
2.4 — How it works
01 — The host facility
Inside the fence line
MicroLink deploys compute inside operating industrial facilities — wastewater plants, food processors, district energy networks. No new building. No greenfield. The host generates value from infrastructure it never paid for.
$0 Host capex
85% Heat to host
11.7K tCO₂e / year avoided
02 — The compute module
Through the door
High-density liquid-cooled compute, deployed through the host's door. Server heat exits as hot water via a plate exchanger — never as wasted air, never mixing with the host's pipes. IT and host remain physically separated at all times.
2.04 tCO₂e / GPU / year saved
21% Grid offset (BTM)
< 0.5 Energy reuse (ERE)
03 — The thermal architecture
Three isolated loops
Server coolant never touches the host's pipes. A plate exchanger transfers heat across the boundary, delivered at the temperature the host process requires. A dry cooler always backstops the rejection path — host and compute carry no dependency on each other.
6 MW Heat to digesters
6.2M m³ Gas displaced / year
100% Loop isolation
Eight zones · then thermal fit detail1 of 4
04 · Eight zones · three clusters · one project
Eight zones of collaboration. Each one with a named owner.
This is how we'd like to work with you. Click into any zone to see the scope, the open questions, and to schedule a working session with the named owner on each side.
Cluster A · The build
Engineering
Grid independence, heat recovery, fabric, monitoring, design. Four zones, four NVIDIA technical owners.
Cluster B · The product
What gets sold
Sovereign public-sector AI on the NVIDIA stack. Sustainability and climate reporting. Two zones, two routes to market.
Cluster C · Contributions
What flows back
Open-source, datasets, semantic conventions. Workforce with SJSU and NVIDIA DLI. Two zones. We want to fill the contribution lane.
Every name on this page is in this room or one degree from it. The four sub-pages below carry the working detail behind Cluster A.
Design · Thermal complementarity
Why MHP and MicroLink waste heat are temperature-complementary
MHP is biological hydrolysis at 75 °C, fundamentally distinct from Cambi or Veolia Exelys thermal hydrolysis at 140 to 180 °C and 5 to 8 bar. The MHP reactor uses Caldicellulosiruptor bescii, a hyperthermophilic anaerobic bacterium, with hydrolysate volatile fatty acids returning to the primary digester for methanogenesis.
The 75 °C operating temperature requires a high-grade heat source — at this site, the cogen jacket water at 85 to 95 °C. MicroLink's 50 °C closed-loop waste heat cannot drive MHP. It can, however, comfortably drive the mesophilic digester loop at 37 °C and the raw sludge preheat from 15 °C to 35 °C. These are exactly the duties that today consume cogen jacket water that would otherwise serve the new MHP module.
IMAGE — MicroscopyCaldicellulosiruptor bescii — hyperthermophilic anaerobe, the organism driving MHP hydrolysis at 75 °C.img-4-1
Site model — WWTP plant and integrated administration building.
The thermal stack is additive, not competitive. Cogen jacket water continues to serve the high-grade MHP duty. MicroLink waste heat substitutes for cogen on the mesophilic loop and feed preheat. The result is roughly 4 to 5 megawatts of recoverable cogen heat freed for redirection — most usefully to the new MHP module, where the high-grade thermal demand is now most concentrated.
Energy balance2 of 4
Design · Energy balance
San José energy balance, today and post-ADFU
The case for MicroLink at San José is not heat supply gap-filling. The plant has more cogen heat available than it needs. The case is thermal substitution: MicroLink absorbs the low-grade duty currently met by cogen, freeing high-grade cogen capacity for the new MHP module and freeing the post-upgrade biogas surplus for monetisation.
TodayPost-2022 cogen, pre-ADFU
Plant electrical demand~11 MW
Cogen output11–14 MW
Cogen recoverable thermal17–19 MW
Plant thermal demand5–7 MW
Heat rejected to atmosphere8–12 MW
Biogas production50,000–65,000 m³/d
Biogas energy600–900 MMBtu/d
Post-ADFU + MicroLink2028–2029
Plant electrical demand12–13 MW
Cogen output14 MW nameplate
Cogen recoverable thermal17–19 MW
Plant thermal demand7–9 MW
Heat rejected to atmosphere→ 0 MW (absorbed by MicroLink)
Two simultaneous shifts. First, biogas production increases by 60 to 80 percent through the combined MHP uplift and FOG co-digestion. Second, plant thermal demand increases only modestly because the new MHP module concentrates duty at 75 °C, not at the mesophilic temperature where most of the existing demand sits.
The combined effect: a substantial biogas surplus the existing 14-megawatt cogen cannot consume at full duty cycle, paired with a heat-rejection problem that has not improved. Both are resolved by a colocated thermal partner.
DIAGRAM — SankeyBiogas energy flow at the post-ADFU plant — cogen consumption, digester thermal duty, MHP HFR duty, and surplus available for monetisation.img-5-1
Site plan — RWF and surrounding context.
Integrated facility section — compute on top, mechanical below, host process beyond.
The integrated facility section illustrates how a MicroLink deployment occupies a compact vertical envelope adjacent to the host process, with the thermal interface running horizontally between them at digester level. The MCFC sits behind the compute envelope, fed by the freed biogas line from the digesters.
Freed value3 of 4
Design · Freed value
Three pathways for the freed biogas at 2026 California prices
The freed biogas — both the MHP and FOG yield uplift and the cogen displacement that MicroLink enables — has three monetisation pathways. We have priced each at 2026 California market terms, drawing on CARB LCFS quarterly transfer reports through February 2026, CPUC Decision 24-08-007, the IRS final rule on Section 45V, the OBBBA, and the Jacobs McLeod and Horrax 2022 hydrogen series.
A
Cogen export and behind-the-meter offset
PG&E SRAC · BioMAT Cat 1 · retail offset
$19/MMBtu
range $8–33
Annual at 5–10 MW IT scale $0.6–4M / year
Recommended
B
RNG injection with LCFS + D3 RIN
PG&E G-BIO interconnection
$20/MMBtu
range $15–25
Annual at 5–10 MW IT scale $1.5–7M / year
C
Hydrogen via Pathway 5 SMR
Biomethane upgrading + SMR
$30/MMBtu
range $22–60
Annual at 5–10 MW IT scale $3–18M / year
Range reflects 45V status uncertainty post-OBBBA.
Pathway B is the primary monetisation route at San José. The all-in value reflects 2026 California market conditions: CARB LCFS pathway value at $5–10 per MMBtu (post-2025 LCFS market amendments), federal D3 cellulosic RIN value at $5–10 per MMBtu, gas commodity at PG&E citygate at $3–4 per MMBtu, and avoided distribution charges. PG&E's Schedule G-BIO interconnection programme provides the technical pathway. SB 1440 capital incentives offset interconnection capex up to $3 million for non-dairy WWTPs. WWTP biogas carbon intensity is structurally distinct from deeply-negative-CI feedstocks like dairy or food-scraps RNG; the figures here reflect a realistic +30 to +55 gCO₂e/MJ Tier 2 pathway.
DIAGRAM — LCFS price trendCalifornia LCFS credit price, 2024–2026, with diesel benchmark and CNG-equivalent pricing overlaid.img-6-1
Aggregate value · central case
Combined gross value at the post-ADFU plant, with a 6 to 10 megawatt MicroLink IT deployment:
approximately $7 to $16 million per year
Freed-biogas pathways: $5–14M/year. Plus the MCFC tri-generation layer adds ~$1.8M/year of behind-the-meter electricity at avoided-cost rates. This is the prize. The commercial structure between MicroLink and the City — the value share between host and developer — is a separate negotiation. This figure illustrates the magnitude, not the proposed allocation.
Two-track partnership4 of 4
Design · Partnership
A two-track partnership proposal
The partnership we propose is structured to protect each party's interests, to fit the ADFU project's design schedule, and to support MicroLink's ability to raise the capital required for the eventual deployment. It runs on two parallel tracks anchored on a sequenced commitment instrument: Expression of Interest, Letter of Intent, Definitive Agreement.
Track 1
The stub-out and the EOI
A future-ready thermal interface, designed and built by Jacobs as a defined scope addition to the existing $200 million ADFU progressive design-build contract.
Three interfaces
Tap on the mesophilic digester recirculation manifold; parallel branch on the cogeneration jacket-water return loop; tap on the raw sludge feed line.
Sized for
A future 5 to 10 megawatt thermal interface, designed by Jacobs to specification, owned by the City as part of the ADFU asset.
Funded by
MicroLink at approximately $1 million, contributed to the City under a Cost-Sharing Agreement structured through San José Charter §1217 (developer carve-out) layered on a Government Code §4217 finding (energy-services framework).
First commitment
A short-form Expression of Interest signed within 30 days, scoped to authorise inclusion of the stub-out concept in the ADFU design-basis discussion. Three EOIs together — City of San José, NVIDIA, Jacobs — anchor the equity raise that funds the stub-out and the eventual deployment.
Track 2
The LOI and the Definitive Agreement
Within 90 days of EOI signature, both parties commit to a full Letter of Intent. Within 9 months, the Definitive Agreement is signed.
Letter of Intent
Captures the technical specification, the commercial framework principles, and the timeline for Definitive Agreement negotiation.
Definitive Agreement
Land licence or lease for the future MicroLink facility on the freed footprint; thermal services agreement; biogas monetisation framework; operational protocols, performance standards, and dispute resolution; right of first negotiation for MicroLink on thermal interface use post-commissioning; information rights on plant operating data; performance milestones and termination provisions.
Trigger
The Definitive Agreement triggers escrow release on the stub-out funding. ADFU stub-out construction proceeds in base scope. MicroLink construction begins, with the modular first-deployment structure operational in the 2028–2029 window.
DIAGRAM — Escrow flowEscrow mechanics: EOI signed (Day 30) → LOI signed (Day 90) → Definitive Agreement signed (Day 270) → escrow releases on the stub-out funding. Capital protected on either path.img-8-1
The trigger
The two tracks are connected by a single trigger structure. The $1 million stub-out funding is held in escrow against execution of the Expression of Interest and releases on signature of the Definitive Agreement. If the Definitive Agreement does not sign — for any reason — the stub-out is value-engineered out of ADFU at no cost to the City, and the escrow returns to MicroLink.
This protects MicroLink's capital, gives the City a structured commitment, gives Jacobs a clean engineering scope, and creates a sequenced set of signed instruments — EOI, then LOI — that supports MicroLink's fundraising.
Eventual deployment scale
Eventual deployment capex$80–120 million
Stub-out contribution$1 million (~1%)
Term of host paymentsTBD in DA
MicroLink team: Nick Searra, CEO & Co-Founder · Sancha Olivier, Design, Site Inspection & Review · Shane Pather, CTO · David Hassler, Sales & Customer · Andrew Thomas, CCO · Deniz Akgul, Capital & Investment Advisor.
The plant1 of 303 · San José
A data centre to be proud of, adapting to the future, close to home.
A place to bring people. A place to be quietly proud of. The first US municipal sovereign AI cloud, on city-owned land, drawing power from biogas the host already produces, returning heat the host already needs. Inside an operating wastewater plant. Seven miles from where the GPUs are designed.
San José and Santa Clara Regional Wastewater Facility. Operating under a Joint Powers Agreement between the City of San José (80%) and the City of Santa Clara (20%), serving 1.4 million residents across eight cities. Treats 416,000 m³ per day [110 MGD] at design capacity 632,000 m³ per day [167 MGD]. Sits on 1,053 hectares [2,600 acres] of city-owned land.
14 MW cogeneration plant on-site. 12 anaerobic digesters running temperature-phased anaerobic digestion. Jacobs-led ADFU upgrade in progress under a $200M progressive design-build contract awarded January 2026.
NVIDIA HQ sits 11 km [7 mi] up the freeway. Bloom Energy headquarters is in San José. SJSU is across the freeway. The partnership graph forms a circle without anyone stretching.
RWF aerial at sunset
Power
From the host's biogas
Power comes from the host plant's biogas, cleaned and run through molten carbonate fuel cells. A hydrogen buffer and lithium-iron-phosphate batteries handle ramp and transient. PG&E grid sits behind everything as last-resort backup.
Heat
Into the digesters
Server reject heat returns to the plant's mesophilic anaerobic digesters at 35 to 38 °C. A stratified buffer tank decouples the data centre's continuous output from the host's variable demand. Surplus heat dumps to dry coolers when the host is at setpoint.
Net effect
Negative grid position
The cogeneration plant's displacement of grid load exceeds the data centre's import. Net grid position is negative. Reported hourly, time-matched, with third-party assurance under ISO 14064-3.
03.B · Who is already at the table
We are walking a process. And it's started.
Four at the table. Eight queued. One adjudicated.
Status legendEngaged · met · ongoingAdjudicated · liveEngagement queued
Engaged · met · ongoing
City of San José · ESD
Joél Cabrera, PE
Senior PM · RWF Digester Upgrade (ADFU)
Our primary technical counterpart on the thermal tie-in. The person rebuilding the digesters that receive our heat.
Jacobs Engineering
Deborah Seibold Egeland
Environmental Regional Solutions Director · data-centre ESG
Our bridge between Jacobs' RWF work and thermal integration. Duke + Stanford.
Prologis · STEM Park
Kevin Havermann
Investment Manager · Data Center capital deployment
Covered STEM Park RFQ from Prologis's side. We've walked adjacency and lease structure.
PG&E · adjudicated, live
Los Esteros 230 kV
June 2025 agreement · 250 MW within 30 to 36 months
Rule 30 (Nov 2024) provides upfront-funded interconnection. Power adjudicated.
Engagement queued · well-understood paths
Mayor's Office
Matt Mahan
Mayor of San José
The narrative principal. AI-forward agenda, GovAI Coalition founding member city, public stand on civic AI.
City of SJ · ESD
Kerrie Romanow
Director · ESD & Chief Sustainability Officer
Landlord and carbon-story signer. Unusual alignment of both portfolios.
City of SJ · ITD
Khaled Tawfik
CIO · Chair, GovAI Coalition
Founder of the ~900-agency coalition NVIDIA signed with in Dec 2024.
Mayor's Office
Stephen Caines
Chief Innovation Officer · Budget Director
Triple-hat role: narrative, budget, senior advisor to the Mayor.
Jacobs Engineering
Maddy Fairley-Wax, PE
Process Engineer · ADFU project lead
Process design lead on the digester upgrade. Owns the technical interface where MicroLink heat enters the host's loop.
San José State University
Cynthia Teniente-Matson, EdD
President · SJSU
Across the freeway from the RWF. Workforce pipeline, applied research partner, civic anchor for the sovereign AI story.
City of Santa Clara
Jovan D. Grogan
City Manager & SVP CEO
Co-landlord of the RWF and NVIDIA's home-city executive.
Santa Clara County
Office of the CIO
Technology Services & Solutions · hosting county
Board ordered countywide AI policy on 24 March 2026. Defined procurement window open.
We are walking into a process already in motion, not starting one.
03.C · The ask from NVIDIA
01
Formally back San José as the reference site. A co-developed reference architecture for a sovereign municipal AI cloud at 5 MW first phase, scaling to 15 MW. Andria's NCP team takes ownership. Public Sector, Magnum IO, and Smart Spaces become channels into the same commercial relationship.
02
Fast-tracked NCP designation track. A working session with Andria's team on certification, NCX Infra Controller integration, ISV validation suite. We bring a live pod spec; we'd like the onboarding playbook, with DGX-Ready Colocation as the realistic first-step framing.
03
A Memorandum of Intent to co-develop San José. Move from technical conversation to a written commitment: NVIDIA and MicroLink working together on the San José site as a sovereign AI reference deployment. Non-binding, scoped, signable in weeks. The signal that takes this from possibility to programme.
The plant1 of 3
03 · San José
Eleven kilometres from NVIDIA's headquarters, we want to build the data centre San José is proud of.
A place to bring people. A place to be quietly proud of. The first US municipal sovereign AI cloud, on city-owned land, drawing power from biogas the host already produces, returning heat the host already needs. Inside an operating wastewater plant. Seven miles from where the GPUs are designed.
San José and Santa Clara Regional Wastewater Facility. Operating under a Joint Powers Agreement between the City of San José (80%) and the City of Santa Clara (20%), serving 1.4 million residents across eight cities. Treats 416,000 m³ per day [110 MGD] at design capacity 632,000 m³ per day [167 MGD]. Sits on 1,053 hectares [2,600 acres] of city-owned land.
14 MW cogeneration plant on-site. 12 anaerobic digesters running temperature-phased anaerobic digestion. Jacobs-led ADFU upgrade in progress under a $200M progressive design-build contract awarded January 2026.
NVIDIA HQ sits 11 km [7 mi] up the freeway. Bloom Energy headquarters is in San José. SJSU is across the freeway. The partnership graph forms a circle without anyone stretching.
RWF at golden hour, looking from north-west toward the bay.
03.A · The energy mix, in words
Power
From the host's biogas
Power comes from the host plant's biogas, cleaned and run through molten carbonate fuel cells. A hydrogen buffer and lithium-iron-phosphate batteries handle ramp and transient. The PG&E grid sits behind everything as last-resort backup, not primary feed.
Heat
Into the digesters
Server reject heat returns to the plant's mesophilic anaerobic digesters at 35 to 38 °C. A stratified buffer tank decouples the data centre's continuous output from the host's variable demand. Surplus heat dumps to dry coolers when the host is at setpoint.
Net effect
Negative grid position
The cogeneration plant's displacement of grid load exceeds the data centre's import. Net grid position is negative. Reported hourly, time-matched, with third-party assurance under ISO 14064-3.
03.B · The people
MicroLink
CEONick Searra
DesignSancha Olivier
CTOShane Pather
CCOAndrew Thomas
SalesDavid Hassler
CapitalDeniz Akgul
City of San José
ESD DirectorKerrie Romanow
CIOKhaled Tawfik
Deputy CMManuel Pineda
RWF Deputy Dir.Kapil Verma
MayorMatt Mahan
Council D4David Cohen
Engineering partner
Process eng.Maddy Fairley-Wax, P.E.
FirmJacobs Solutions
Contract$200M ADFU, Jan 2026
The Jacobs Microbial Hydrolysis Process and MicroLink compute waste heat are designed for adjacent jobs at the same site.
03.C · The ask from NVIDIA
01
Formally back San José as the reference site. A co-developed reference architecture for a sovereign municipal AI cloud at 5 MW first phase, scaling to 15 MW. Andria's NCP team takes ownership. Public Sector, Magnum IO, and Smart Spaces become channels into the same commercial relationship.
02
Fast-tracked NCP designation track. A working session with Andria's team on certification, NCX Infra Controller integration, ISV validation suite. We bring a live pod spec; we'd like the onboarding playbook.
03
One named ISV introduction. Route us to the right partner for the Kubernetes and multi-tenant orchestration tier on the pod. Mirantis k0rdent is the hypothesis. We want NVIDIA's recommendation.
03 · Site
San José–Santa Clara Regional Wastewater Facility
The RWF is the second-largest advanced wastewater treatment plant in the western United States. Owned jointly by the City of San José (~80%) and the City of Santa Clara (~20%) under a 1959 joint powers agreement, operated by San José Environmental Services. It treats an average of 416,000 cubic metres per day (110 MGD) against a permitted capacity of 632,000 cubic metres per day (167 MGD), serves 1.5 million residents across eight cities and four sanitary districts, and discharges treated effluent to Artesian Slough.
The digester complex consists of twelve covered tanks of approximately 3,785 cubic metres each, totalling roughly 45,400 cubic metres of active volume. The plant operates a temperature-phased anaerobic digestion train: four thermophilic stages at 50 to 55 °C feeding into eight mesophilic stages at 35 to 37 °C. The 14-megawatt cogeneration facility was designed and built by Jacobs and came online in 2022 — DBIA 2021 National Award of Merit. The dewatering facility came online in 2025 at $164 million.
IMAGE — Site overviewRWF aerial showing the twelve digester tanks, cogen building, and active plant zone.img-3-1
Average flow416,000 m³/d (110 MGD)
Permitted capacity632,000 m³/d (167 MGD)
Service population1.5 million
Digester volume45,400 m³ (12 MG)
Cogen capacity14 MW (4× Caterpillar, 2020)
Site footprint, total1,050 ha (2,600 acres)
Recycled water8 MGD (SVAWPC)
Flood protection$197M levee, Sept 2025
Capital programme$2.1B (largest in city history)
Freed by Dewatering (2025)~750 acres (305 ha)
The ADFU project2 of 3
03 · Site · ADFU
The Additional Digester Facility Upgrades programme
On 21 January 2026, the City selected Jacobs as progressive design-build contractor for the $200 million Additional Digester Facility Upgrades. The base scope covers structural, mechanical, electrical, and instrumentation renewal of the eight mesophilic digesters, replacement of floating covers with fixed covers, electrical upgrades, a new fats/oils/grease receiving station, and integration of Jacobs' proprietary Microbial Hydrolysis Process.
The project is currently in Phase 1 progressive design-build (preliminary services, $9.54 million envelope, plus up to $10 million in pre-authorised Early Work Packages). Phase 1 closeout and Guaranteed Maximum Price (GMP) execution are projected for late Q4 2026 to Q1 2027. The actionable window for low-six-figure cost on incremental scope is April through August 2026 — before the 30% design milestone in late summer. After that, scope additions process as formal change orders at materially higher cost.
A note on the Silicon Valley context. Digital Realty's SJC37 (48 MW) and Stack Infrastructure's SVY02A (48 MW) in Santa Clara are both fully constructed and entirely vacant — Silicon Valley Power's $450 million grid upgrade does not complete until 2028. The MicroLink site sits in PG&E territory with a 250 MW Implementation Agreement already in place. Modular containerised compute can be energised in 12 to 16 weeks, bypassing the multi-year grid queues that have stalled every other Silicon Valley deployment.
IMAGE — Jacobs pressJacobs press release, 21 January 2026 — ADFU contract award announcement.img-3-2
CityCity of San José
Co-ownerCity of Santa Clara
EngineerJacobs Solutions
ConstructorWalsh Construction
ConcreteStructural Technologies
Programme mgmtStantec
City PMJoel Cabrera, P.E.
Jacobs EVPGreg Fischer
Contract value$200 million
Contract typeProgressive design-build
Strategic context3 of 3
03 · Site
Why this site, why now, why this configuration
Why this site
The freed Dewatering footprint at the RWF — approximately 750 acres (305 hectares) of City-owned, industrial-zoned land inside the operating fence line, freed by the $164 million Dewatering Facility commissioned in 2025 — is the largest piece of available industrial-zoned land at any major California wastewater treatment plant. It sits within thermal-pipe distance of the digester complex. The City has formally announced an intent to lease this land for clean-tech tenants and has issued an RFQ for up to 99-year leases (Keyser Marston Addendum No. 2, June 2025).
Why now
Mayor Matt Mahan announced his candidacy for Governor of California on 29 January 2026 with the primary on 2 June 2026. His public platform centres on tech infrastructure, AI, and data centre attraction — the City's $2.6 billion PG&E partnership (July 2025) pre-allocated 250 MW for up to ten large data centres in the South Bay. Deputy City Manager Manuel Pineda — formerly Chief Electric Utility Officer at Silicon Valley Power, now the City's operational champion on data centre attraction — has publicly described San José as "open for business for data centers." District 4 Councilmember David Cohen, in whose district the RWF sits, chairs the Transportation and Environment Committee and is also Vice-Chair of the Treatment Plant Advisory Committee. The political alignment in this window is unusually favourable.
Why this configuration
MicroLink's first deployment at this site is sized for a small modular footprint — approximately 1 to 2 hectares — connected to the thermal stub-out via short pipework runs. The configuration is deliberately compact and proximate to the digester complex, designed to validate the thermal-fit thesis at operating scale before committing to permanent infrastructure. The 750 acres provides ample optionality for future expansion. We expect to lead with a temporary or leased structure that can be relocated if conditions change — a posture appropriate to a first-of-kind deployment, distinct from the larger industrial-park developments contemplated elsewhere on the freed footprint.
SITE MAP — Strategic sitingSite map — RWF aerial with active treatment plant, freed Dewatering footprint (~750 acres / 305 ha), and indicative MicroLink siting near the digester complex.img-3-3
Production version will use georeferenced satellite imagery with the proximate siting strategy clearly indicated.
Political environment
Mayor Matt MahanGubernatorial candidate · primary 2 June 2026
DCM Manuel PinedaOperational champion · data centre lead
CM David Cohen (D4)RWF in district · T&E Chair · TPAC Vice-Chair
ESD Director Jeff ProvenzanoAuthored Climate Adaptation Plan (Mar 2026)
SJ Clean Energy leadErica Garaffo
Vision rendering — integrated sustainability complex at scale.
Two motions · then five invitations1 of 4
05 · What's ahead · Beyond today · Beyond San José
1 North America2027 · Co-published
Reference architecture for sovereign municipal AI
Every US city with a wastewater plant or district energy network can use the template.
AnchorNVIDIA Public Sector
2 NCP commissioningH1 2028 · Joint
Heat-recovery commissioning playbook
A one-off integration becomes a deployable pattern.
OutputDGX-Ready Colocation pattern
3 Europe2027 · Regulatory window
EU EED 2027 compliance template
Every hyperscale operator with EU data centres needs to demonstrate waste-heat utilisation.
ReachUK · DE · NL · JP follows
4 Next horizon2028 onward · Open
The non-federal public sector reference
State, local, international public-sector AI without a hyperscale dependency.
StatusProvisional frame
05.B · Motion two · the Choice Hotels edge rollout
Choice Hotels is the edge.
A 25-site Phase 1 with Choice Hotels, scaling to 200 properties in Phase 2 and to thousands in Phase 3 across the broader hospitality network. Sub-megawatt pods at each property using NVIDIA Jetson Orin and IGX at the host edge, federated back to regional cores at MicroLink wastewater and brewery sites using Spectrum-XGS for site-to-site collective bandwidth.
The motion connects MicroLink's flagship sites to a distributed network of host-coupled edge nodes. Each hotel is a thermal sink and a regional inference point. The sovereign AI cloud delivered at San José becomes accessible to every property under the same commercial framework.
Why both motions need you in the room today
The two motions look like different businesses. They're not. They share the same thermal model. The same federation fabric. The same host-coupled commercial logic. They share a single customer story: "AI infrastructure that fits inside what already exists."
That story is told in Public Sector for San José. In Smart Spaces for Choice Hotels. In EMEA for the next twenty European cities. In Telco for sovereign-cloud-on-host-infrastructure. Every NVIDIA org in this meeting has a stake.
05.C · A closing thought, from personal experience
I lived in Lagos for five years. Then Nairobi for five more. In 2001, if you weren't in the same room as someone in Nigeria, they were unreachable. No reliable post. No working landlines for most of the country. Then GSM arrived. Half a million subscribers in 2001. Eighty million by 2010. Two hundred and twenty million today.
A continent didn't get phones. A continent got each other.
The shift we are inside today is the same scale. AI infrastructure is the next thing that becomes invisible because it's everywhere. It can be done well, or it can be done expediently. We are here to do it well, with the people in this room, starting at one site we can all be proud of.
Nick Searra · CEO and Co-Founder
05 · Path forward
What we'd like to build, together
This brief is prepared for one conversation with one person. We have built a thesis that we believe sits in your domain, your judgement, and your intellectual interest. What follows is what we would love to do together — not what we are asking from you. Each invitation is structured around your authority and your sense of timing.
MicroLink reference architecture — the category we'd build together.
RoleProcess Engineer
FirmJacobs Solutions
OfficeDenver
Lead authorWEFTEC 2024 (MHP)
AlsoEuropean Biosolids 2024
ChairWEF Residuals & Biosolids Community Bioenergy Subcommittee, 2025–26
Five invitations
01
Work through the technical thesis with us. Push back on the temperature complementarity argument. Tell us where the heat balance is wrong. Tell us where MHP integration with the existing TPAD train would surprise you. We have built a thesis we believe is defensible — we want it stress-tested by the person who knows the process best.
02
Co-develop the global strategy. Beyond San José: 276 large WRRFs in the United States, 690 in Europe. What does this category look like as a Jacobs–MicroLink offering? We would love to do this thinking with you, not present it to you.
03
Bring this into the conversation with NVIDIA. NVIDIA is our go-to-market partner. The technical narrative is stronger when a Jacobs process engineer is at the table. We would like you to be part of those conversations from a point that feels right to you.
04
Help us widen the conversation with the City and the public sector. Joel Cabrera originated this introduction and the City has been the catalyst. As the technical anchor, your judgement on how that conversation deepens — what it touches, who it includes, when it expands — is what we would like to follow.
05
Pull in others from your team, at your pace. Whoever you see as natural collaborators. The dyad pattern that productises this category needs more than two of us — we expect it. We move at whatever cadence and structure you find right, and we follow your lead on who joins the conversation when.
The generation we design First Light around. Drop-in compatible with NVL72 infrastructure. 3.3× compute of Blackwell Ultra. The platform ML-SJ10 ships on.
ML-SJ10Energizes 2027
H2 2027Next
Rubin Ultra
NVL576 · Kyber rack · HBM4e
Four reticle-sized GPUs per socket. 600 kW per rack. 14× the GB300 NVL72. The rack architecture ML-SJ10 was designed for from the loop up.
Pre-release targetReady day one
2028Horizon
Feynman
Rosa CPU · LP40 · BlueField 5
3D die stacking. Custom HBM. NVLink switches with co-packaged optics. The first generation where San José physical-AI workloads mature into production at city scale.
Pre-release targetGlobal reference
2029 +Future
Post-Feynman
Annual cadence · public-sector-ready
The generations not yet named publicly. MicroLink's sovereign-compute architecture scales across every generation that comes after.
Hub replicationGlobally
What we validate in San José, MicroLink deploys everywhere. Pre-release hardware access is what lets the public sector ship on release dates, not 18 months after.
The deployment hub Every generation
Market case2 of 4
05 · Path forward · The market case
What this becomes, beyond San José
San José is the first instance of a model that travels. The defensible US addressable market is 276 large wastewater resource recovery facilities operating anaerobic digestion. Roughly two thirds of those plants sit inside Jacobs' active client orbit. The European market roughly doubles the long-run prize. Sources: EPA Clean Watersheds Needs Survey 2022; EPA Opportunities for CHP at Wastewater Treatment Facilities; ENR rankings; Jacobs FY2024 reporting.
ENR / Jacobs FY24 300+ water and wastewater facilities under engagement.
Methodology
Plant counts drawn from EPA's 2022 CWNS for the 17,544 POTW total and from EPA's "Opportunities for CHP at Wastewater Treatment Facilities" plant-size distribution. The 276 figure is the subset operating anaerobic digestion at production scale. MW of absorbable IT load is calculated by site-size band: 1–2 MW thermal absorbable per 10 MGD plant, scaling to 5–15 MW per 100 MGD plant. Revenue at MicroLink's 2026 wholesale rate of $170 per kW per month. EBITDA at 50% margin reflecting NOAK unit economics. The Jacobs channel slice triangulates from ENR ranking, Jacobs' 2024 disclosure of "300+ water and wastewater facilities" under engagement, and a public-record sweep of major design-build, EPCM, and O&M contracts from 2022 through January 2026.
European optionality
Roughly 690 large WRRFs across the EU and UK could host more than 1 MW of IT load each. Germany leads (around 220 sites), the UK (around 120), and combined Italy/Spain/France (around 200). Districts with established fourth-generation district heating networks — Denmark, the Netherlands, southern Sweden — substantially expand the absorbable thermal sink because excess heat above digester demand can flow into the local network rather than into a dry cooler. Capturable EU revenue over a ten-year horizon is between $1.0 and $1.6 billion.
Geography
Plants
Capturable revenue (10-yr)
EU + UK
~690large WRRFs
$1.0–1.6B10-year horizon
Political framework3 of 4
05 · Path forward · The political framework
Three entities. One pathway. A coordinated public-sector AI infrastructure model.
The opportunity at San José is not just a deployment. It is a template for how the public sector partners with industry to stand up AI compute infrastructure responsibly. Three entities, working together, define the pathway: NVIDIA as the certified compute partner; Jacobs as the engineering authority; MicroLink as the heat recovery infrastructure operator. Together we bring government — Mayor's office, City Council, the Treatment Plant Advisory Committee, and the State of California — into a coordinated structure that delivers public infrastructure value at zero ratepayer cost.
The compute
NVIDIA
NVIDIA Cloud Partner programme certifies the deployment. The two-track partnership covers this site and a global public-sector partnership for sovereign and municipal AI compute. Final NCP approval expected within two weeks.
The engineering
Jacobs
Jacobs Solutions, ranked #1 in wastewater treatment by ENR for nine consecutive years, holds the City's $200 million ADFU contract. The integration system is co-developed with Jacobs as the technical authority on digester process and resource recovery.
The heat recovery
MicroLink
MicroLink owns the thermal architecture (ML-IND-001), the heat recovery operation, and the relationship with the public-sector host. We deploy the modular compute facility, operate the heat recovery, and deliver the value share back to the host.
Three entitiesNVIDIA · Jacobs · MicroLink
→
CentreGovernment
→
OutcomePublic-sector AI infrastructure
Outcomes: zero ratepayer impact · 6–10 MW of municipal AI compute capacity · $5–14M/year of unlocked biogas value · 8–12 MW of waste heat captured · a category-defining public-sector AI infrastructure model.
The mayor brings the political alignment. NVIDIA brings the customer demand. Jacobs brings the engineering authority. MicroLink brings the heat recovery thesis and the deployable asset. Together we define how cities, states, and nations stand up AI infrastructure on existing public-sector sites — with engineering rigour, political legitimacy, and climate integrity.
Global benchmark4 of 4
05 · Path forward · The global benchmark
Beyond a single deployment. A category we define together.
San José is the first instance. The category is the integration of compute waste heat with anaerobic digestion at wastewater treatment plants — a model that travels across 276 large US WRRFs, ~690 European WRRFs, and analogue infrastructure globally. We are proposing not a deployment for you to bless, but a category for you to define.
MicroLink + Maddy
We are the data centre professionals. You are the digester professional. Together we have the rare combination required to define this category authoritatively: deep operational experience on both sides of the thermal boundary, a published technical thesis (Egeland 2023; McLeod & Horrax 2022; your own WEFTEC 2024 lead-author paper on MHP), and a flagship deployment site that lets us validate the integration model at operating scale.
The work we propose is co-development of a defined integration system: pre-engineered components, validated controls logic, a repeatable deployment package, a published case study from San José, and a co-authored technical paper at WEFTEC 2026. You become the named technical anchor — the dyad pattern Tier 1 EPCs use to anchor productised offerings, with you as the public technical voice and a senior co-sponsor on the Jacobs side.
This is materially more than a paper. It is the foundation for a generalisable system that Jacobs can deploy across its WRRF client portfolio and MicroLink can offer to any compatible host site globally.
The opportunity at scale
Tier 1 — North American deployment
~180 plants in the Jacobs orbit
~500 MW IT addressable. ~$1.0 billion annual revenue at NOAK scale. ~$0.5 billion annual EBITDA.
Tier 2 — European replication
~690 large WRRFs across the EU and UK
Districts with district heating networks (Denmark, Netherlands, southern Sweden) materially expand the absorbable thermal sink. ~$1.0–1.6 billion capturable revenue over a 10-year horizon.
Tier 3 — Global category
Wastewater treatment plants with anaerobic digestion globally
APAC, Middle East, Latin America. The integration model defined here becomes the reference for how compute waste heat couples to municipal infrastructure worldwide.
The numbers are the prize. The work is the path. We are asking you to lead the technical definition of this category, alongside MicroLink, anchored to the San José deployment and extending to wherever the model travels. Tomorrow's meeting starts that conversation.
"Every city has a wastewater plant. Every wastewater plant needs heat. Every data centre makes heat. First Light is the proof that the equation closes."
MicroLink Data Centers · First Light · April 2026
The category, sketched.
Engagement timeline
Lane
D0D14D30D90D180D2702027202820292030
EngagementMaddy → City
EOI drafting
CapitalEquity raise
Equity raise vs three EOIs
AgreementEOI → LOI → DA
LOI drafting
DA negotiation
BuildStub-out → operational
Stub-out construction
ADFU comm.
MicroLink construction
Day 0 — 29 April 2026 — this meeting. Day 14 — NCP approval expected. Day 30 — EOI signed (City + NVIDIA + Jacobs). Day 30–60 — equity raise opens against the three EOIs. Day 90 — Letter of Intent signed. Day 270 — Definitive Agreement signed; escrow releases; ADFU stub-out construction begins. 2027–2028 — ADFU project commissions. 2028–2029 — MicroLink modular deployment construction. 2029–2030 — first-of-kind site operational.
06 · The ask · What we leave this room with
01Primary
NCP onboarding track.
A working session on certification, NCX Infra Controller integration, ISV validation suite. We bring the live pod spec; you bring the playbook.
Andria ZouSenior Director, Global AI Data Center Strategies
02Technical
DSX Max-P as a first-class mode.
Same API as Max-Q. Opposite objective: maximise sustained thermal output when the host demands heat. Roadmap commitment or co-development. We have the field data to calibrate.
Karthik MandakolathurProduct Manager, Magnum IO
03Ecosystem
One named ISV introduction.
Route us to the right partner for the Kubernetes and multi-tenant orchestration tier on the pod. Mirantis k0rdent is the hypothesis. We want your recommendation.
Danny ZaidifardBD, Strategic Partnerships
We've spoken enough
The link will be shared in the chat.
The eight zones live there. Click into any one. Schedule a working session with the named owner. The first follow-up belongs to whoever wants it most.
We want to build the operational template, with you, here. Then take it everywhere.
06.B · Prior conversation · the engineering partner anchor
The record below is the 29 April working session with Jacobs Solutions, the engineering and integration partner at San José. It sets the engineering ground state into which the NVIDIA partnership lands.
06 · Meeting record
Maddy Fairley-Wax & Nick Searra A first conversation
29 April 2026 · Video call · 60 minutes
Date29 April 2026
FormatVideo call
Duration60 minutes
JacobsMaddy Fairley-Wax, P.E.
MicroLinkNick Searra
Next callFollowing week — Jacobs AD technical director joining
6.1 — Overview
A first technical conversation between Maddy Fairley-Wax, P.E. (Process Engineer, Jacobs Solutions) and Nick Searra (CEO, MicroLink Data Centers). The intent of the meeting was to introduce the MicroLink thesis, test the technical complementarity with the San José ADFU programme, and explore whether a deeper Jacobs–MicroLink collaboration is of mutual interest.
6.2 — What was discussed
The MicroLink thesis. MicroLink builds heat-recovery infrastructure for liquid-cooled data centres, deploying compute inside operating industrial sites where the rejected heat does useful thermodynamic work. The conversation focused on the San José–Santa Clara Regional Wastewater Facility as a candidate site, and on the broader category of wastewater treatment plants as host facilities for this architecture.
Liquid-cooling trajectory. Server cabinet power is moving from 7–12 kW per rack today to a projected 500–600 kW per rack within the next generation, making air cooling thermodynamically impractical. Direct-to-chip liquid cooling is the industry direction. MicroLink's architecture takes advantage of that thermal output rather than dissipating it.
The proposed thermal exchange. A two-way relationship: MicroLink takes biogas from the plant for behind-the-meter electricity generation (via molten carbonate fuel cell or hydrogen storage), and delivers waste heat from the servers at 45–55 °C to the digester train and sludge drying processes. That outlet temperature can be lifted to ~75 °C by routing through Bitcoin-miner racks at the tail of the loop, and to much higher temperatures via a heat pump. The data centre acts as a thermal augmentation source, offsetting the plant's biogas use for heating.
The NVIDIA partnership. MicroLink is in active discussions with NVIDIA on two parallel partnership tracks. The San José site is one of several under evaluation, alongside Newtown Creek (Brooklyn), Stickney (Chicago), and West Point (Seattle). The proximity of San José to NVIDIA's headquarters (~7 miles) makes it a natural candidate for technology co-development, including digital-twin integration and AI-monitored operations.
Site benchmark ambition. The intent at San José is to deliver a category-defining first-of-kind reference: a deployment that other wastewater treatment plants globally can model from. The collaborative framework — including Jacobs as the engineering, procurement, and construction partner — is the structure within which that ambition would be realised.
6.3 — Technical contributions from Jacobs
Several elements of MicroLink's working thesis were materially refined or corrected during the conversation. These contributions are recorded here with attribution because they will shape the next iteration of MicroLink's technical specification and the joint paper proposed below.
Cogeneration heat is already recovered. The San José cogeneration system does not reject 8–12 MW to atmosphere as previously assumed. The cogen recovers heat from the internal combustion engines via hot-water loop (~80–85 °C) and delivers it to the digesters through heat exchangers. This reframes the "heat surplus" thesis: the opportunity is not to recover wasted heat, but to augment a heat supply that is already in service. (Maddy Fairley-Wax)
Cogeneration cost reference. The current San José cogen system was installed in 2017 at approximately $20 million. With cost escalation, an equivalent system today would cost $60–70 million. This figure is material to the financial framing of any future deployment. (Maddy Fairley-Wax)
Microbial Hydrolysis Process — quantified. MHP is a side-stream process targeting hard-to-digest cellulosic material via specialised bacteria. It consistently delivers 75% conversion of organics to biogas, against the ~60% conversion of conventional anaerobic digestion. It also reduces downstream solids volume, with implications for equipment sizing across the bio-solids train. The first full-scale MHP facility is currently under construction in Denmark. (Maddy Fairley-Wax)
Anaerobic digestion temperature regimes. Digesters operate at either 35 °C (mesophilic) or 55 °C (thermophilic). The San José tanks are approximately 3 million gallons each. The dominant heat duty is raising raw thickened solids (4–6% solids content) from inlet temperature (~15–20 °C) to digestion temperature. (Maddy Fairley-Wax)
Ideal-case design preference. In a clean-sheet design, the preferred process train would be: thermal hydrolysis pre-treatment, feeding digesters at up to 10% solids content, followed by thermophilic anaerobic digestion paired with MHP as a side-stream. This is the configuration most likely to maximise conversion and minimise downstream solids. (Maddy Fairley-Wax)
Industry context. Sacramento has a $140M, 15 MW biogas utilisation contract — a relevant comparator for the scale of capital being deployed in the sector. Many facilities flare biogas because the capex for beneficial use does not pay back at low utility rates. (Maddy Fairley-Wax)
Sludge nomenclature. "Sludge" refers to the combined primary and secondary solids stream. Raw sludge is pre-digestion; digested sludge is post-digestion. Cellulose content in municipal wastewater comes substantially from toilet paper. Composition is broadly stable across municipalities except where industrial contributors dominate (e.g. Duluth, MN, with ~50% paper-mill influent). (Maddy Fairley-Wax)
These contributions are gratefully acknowledged. They are the substance of what makes this kind of conversation valuable, and they will be carried forward in MicroLink's thinking and in any joint technical work that follows.
6.4 — Heat-recovery system architecture
MicroLink described a three-loop system for heat transfer between the compute envelope and the host process. The compute side runs a closed-loop glycol mix at the server cold plates. A secondary closed loop transfers heat across the boundary via plate, tube-and-tube, or spiral exchangers — selection depending on host operator preference, capital constraints, and existing equipment. The tertiary side is the host's existing digester heat-supply loop.
6.5 — What was agreed
01Maddy Fairley-WaxProvide rough cost data for cogen system installation, with reference to a comparable Michigan wastewater treatment plant project
02Nick Searra & Maddy Fairley-WaxContinued discussion on collaboration on an academic paper exploring the integration of WRRF design with data-centre infrastructure
03Maddy Fairley-WaxInvite Jacobs' technical director — global expert on anaerobic digestion and bio-energy — to the next call
04Nick SearraSend follow-up email with the brief link and scheduling options for next week
05Maddy Fairley-WaxSubject to client confirmation, share microbial hydrolysis information and biogas calculations specific to San José
06Nick SearraSend follow-up email to Joel Cabrera (City of San José)
6.6 — What comes next
A second meeting is scheduled for the following week, with Jacobs' anaerobic digestion technical director joining. The conversation will move from concept to specifics: how a real San José deployment is sized, where MHP would integrate with MicroLink's thermal output, what data Jacobs is able to share under client confidentiality, and what the structure of a joint technical paper would look like.
Maddy Fairley-Wax was clear that this conversation does not constitute a "yes" on partnership — and equally clear that it is not a "no". The next call is the next step. The work between now and then is technical preparation, data sharing where permitted, and the start of the academic collaboration.
A1 · Questions
Five questions we would love your view on
Not a questionnaire. A way of opening a conversation we hope continues beyond the meeting. These are the questions we keep thinking about: the ones where your perspective would change how we think. Rank what resonates, write your own, or both.
01
On the next decade
Where will sovereign and municipal AI infrastructure look most different five to ten years out?
The genuine inflection points are usually visible before they become consensus. We want to know which of these you think will move the most, and which one will move first.
Rank your top three0 of 3
0 / 1500
Thank you. 0 people have shared their view on this so far.
02
On the compute and host boundary
Where does the seam between compute and industrial process go next?
Integration is happening at thermal, electrical, control, and commercial layers, each one a separate negotiation today. We want to know where the deepest unlock sits, and what blocks it inside NVIDIA's reference designs right now.
Rank your top three0 of 3
0 / 1500
Thank you. 0 people have shared their view on this so far.
03
On the public-sector path
Where is there room for state, municipal, and non-federal public buyers in NCP?
The program today reads as built for hyperscalers and federal-scale sovereigns. The gap is real, the demand is real, and it is happening with or without an NVIDIA-recognised path. We want to know what would unlock that path internally.
Rank your top three0 of 3
0 / 1500
Thank you. 0 people have shared their view on this so far.
04
On heat as a first-class output
What would make heat recovery a default specification rather than a project-by-project negotiation?
Server heat into industrial process is standard in district heating across Northern Europe and is becoming standard in our deployments. We want to know what would tip it from edge case to expected default.
Rank your top three0 of 3
0 / 1500
Thank you. 0 people have shared their view on this so far.
05
On San José
What is the question you would most want this site to answer first?
San José is one site, one set of conditions, and a chance to learn things that scale to other public-sector deployments. If you were sitting in the design review, what would you most want this site to settle?
Rank your top three0 of 3
0 / 1500
Thank you. 0 people have shared their view on this so far.
A2 · LIBRARY
The collection of MicroLink Briefings.
Domain knowledge we accumulate as we work with partners. Each briefing is a working document.
WRRF REFERENCE · V1 · APRIL 2026COMPLETE
Wastewater treatment, a working reference.
A briefing on wastewater treatment processes: anaerobic digestion, MHP, thermal hydrolysis, cogeneration, biogas pathways, and how MicroLink integrates with them. Originated from a technical conversation with Maddy Fairley-Wax (Jacobs Solutions).
Quantum-X800 + AC SU at 576 GPUs, three-loop thermal architecture, diesel-free 2N power topology. We want to write the reference architecture for the canonical pod with NVIDIA, so the document reads as a joint template that other deployments can adopt.
SOVEREIGN MUNICIPAL AI · IN DEVELOPMENTOPEN INVITATION
The product, end to end.
Confidential Computing on Hopper / Blackwell, BlueField-3 multi-tenant isolation, Run:ai per-tenant clusters, Llama-Nemotron sovereign fine-tuning. We want NVIDIA's product and public-sector teams to co-author this with us, so the stack is documented the way both organisations would describe it.
More briefings to follow, added as the work continues.
A2 · References
Glossary, sources, and citations
Technical terminology used throughout this brief, followed by the primary, regulatory, and industry sources behind the figures and claims.
Glossary
ADFU
Additional Digester Facility Upgrades; the $200 million Jacobs progressive design-build contract awarded by the City of San José in January 2026.
CDU
Coolant Distribution Unit; isolates the chip-side fluid loop from the facility loop and provides redundant pumping.
CI
Carbon intensity, expressed in grams of CO₂-equivalent per megajoule, used by CARB LCFS.
CIN / TAN / SMN
The three Ethernet/InfiniBand fabrics in the NCP architecture: cluster interconnect, tenant access, and secure management.
D3 RIN
Federal cellulosic Renewable Identification Number under the EPA Renewable Fuel Standard, Pathway Q for RNG dispensed as transportation CNG.
DA
Definitive Agreement; the substantive partnership contract concluding the EOI → LOI → DA sequence.
DTC
Direct-to-Chip liquid cooling; cold plate mounted directly on the GPU/CPU package.
EOI
Expression of Interest; the short-form first-commitment instrument signed within 30 days of the meeting, scoped to authorise inclusion of the stub-out concept in the ADFU design-basis discussion.
GMP
Guaranteed Maximum Price; the second-phase commercial structure of the ADFU progressive design-build contract.
HFR
Hydrolysis Fermentation Reactor; the 75 °C sidestream vessel in the Jacobs MHP three-vessel architecture.
HRT
Hydraulic Retention Time; reactor volume divided by daily volumetric feed.